Connections, system strength and curtailment

Diagnose connection and operational constraints.

Understand · 1 of 4Self-paced

Diagnose a connection bottleneck

A connection assessment tests the plant in its network context. Power flow, stability, system strength and performance standards answer different questions. A technically connected plant may still face operational constraints and curtailment.

Read · work through an example · try it yourselfWatch the video
Working relationship

Export capability = minimum of applicable plant and network limits

What to keep separate

Do not infer unconstrained market access from a signed connection agreement.

Your task

Create a constraints register separating connection conditions from market-dispatch constraints and planned outages.

Watch the explanation

Key terms in plain English
MW
Megawatt: a measure of power, or how quickly energy is transferred. A plant's maximum MW is not its actual output in every interval.
Curtailment
A reduction in generation below what could otherwise have been produced. Network limits, system security and commercial decisions can have different causes.