Forecast demand without leakage
Define the demand measure before modelling it. Operational demand differs from underlying consumption when behind-the-meter generation changes. Validate in time order and use only predictors that would have been available when the forecast was issued.
The lesson
4 chaptersBrowse the chapters
01Define a forecast that can actually be tested
Specify target, issue time, horizon, geography and use. Forecasting a site's demand at 09:20 from information available at 08:55 differs from predicting a regional evening peak one day ahead. The linked lab forecasts the same six site-demand intervals used in Topic 31. It does not estimate AEMO operational demand or represent a fitted production model.
Start with a baseline you could run at decision time, such as an appropriately selected previous-day or previous-week profile. A candidate model must beat that baseline on a relevant task, not merely fit the historical observations more closely. Preserve forecast issue times and the inputs that were available when each prediction was made.
For a real operational-demand project, define the published demand measure and its boundary before building features. Rooftop generation, embedded load, weather and calendar effects can alter the interpretation. A meter-level model, regional demand forecast and connection capacity assessment are different products even if each uses MW.
02Use chronological evidence, not a convenient random split
Choose training, model-selection and final-test periods in time order. Learn transformations such as scaling or missing-value treatment on training data only, then apply them to later periods. Do not select a model after repeatedly checking the final holdout and still call that holdout independent.
A rolling-origin exercise repeats the decision: fit using data available up to one origin, predict the intended horizon, score it, then move forward. Match the horizon to the work requirement. A five-minute-ahead result does not establish day-ahead performance; a model benefiting from updated weather cannot fairly be compared with one denied that information.
The lab supplies invented forecasts issued before the observations. You can practice scoring but cannot verify their training history or infer generalisation from six rows. Extend the method to multiple weeks, seasons and stress periods using timestamped input vintages before making an operational recommendation.
03Explain the error in units and consequences
Define signed error as actual minus forecast. Positive means under-forecast demand; negative means over-forecast. MAE averages absolute errors and retains MW units. RMSE emphasises larger misses. Signed mean error measures bias, but positive and negative misses can cancel. Use the same valid intervals for every model comparison and report exclusions.
In the lab, baseline errors are 0, 20, 20, 20, −20 and 20 MW: MAE 16.67 MW and mean error 10 MW. Candidate errors are −5, 5, 10, −10, −5 and 5 MW: MAE 6.67 MW and mean error zero. Zero average bias does not mean zero errors. A lower average error also does not ensure better performance at the highest-cost interval.
Convert an error to a commercial exposure only after defining a mechanism. A 10 MW under-forecast for five minutes is 0.8333 MWh; a stated A$120/MWh incremental price difference implies A$100 of incremental cost in that simplified scenario. Multiplying by a spot price without explaining procurement, hedging and settlement does not establish the actual financial loss.
04Promote a model through review, not through one score
Plot actual and forecast MW on the same labelled time axis. Inspect when the misses occur: peaks, ramps, missing measurements or an unusual event. Use a separate error plot or error table to identify patterns concealed by a single average. Report sample size and the operating periods represented.
Define acceptance before comparing models: baseline performance, peak-error tolerance, data freshness, runtime, fallback and monitoring owner. A candidate might lower MAE but be rejected if it fails during the critical peak or depends on unavailable inputs. Prediction intervals require their own coverage checks; a point forecast is not a confidence band.
Your memo should recommend a next test rather than declaring production readiness from the lab. Specify additional periods, input-vintage checks, retraining boundaries and a trigger for reverting to the baseline. Keep a versioned change record so someone can reconstruct which model generated a particular decision.
Watch the explanation
Key terms in plain English
- MW
- Megawatt: a measure of power, or how quickly energy is transferred. A plant's maximum MW is not its actual output in every interval.
Supporting diagrams
A smaller error is evidence, not approval
Score identical observations with the same sign convention.
- 01 · Baseline16.67 MW MAE
100 MW absolute error total across six observations
- 02 · Candidate6.67 MW MAE
40 MW absolute error total across the same six observations
- 03 · Next gateUnseen periods
Test peaks, stability and information availability