Reconstruct an event without hindsight bias
Build a timeline using prices, dispatch, bids, constraints, flows and notices. Keep what was known at decision time separate from later revised data. Test a competing explanation instead of fitting a story to a chart.
The lesson
6 chaptersBrowse the chapters
01Start with the decision clock
An event analyst answers two different questions: what happened, and what action was reasonable with the information available at the time? A later report may improve the first answer without proving that a trader or operator could have known it earlier. Write the decision time, region, participant role and purpose at the top of the analysis before collecting charts.
Create a timeline with separate columns for event time, interval label, publication time, data revision, source and interpretation. An outage occurring at 10:02, an interval labelled 10:05 and a notice published at 10:07 are not three simultaneous observations. Preserve the stated time zone and establish whether interval timestamps denote beginnings or endings. A five-minute discrepancy can be a labelling issue rather than conflicting evidence.
Make two views of the evidence: an as-known-at-the-time view and a later reconstructed view. If a field was not published until after the decision, it can help review the event but cannot be silently used to justify the earlier decision. Your deliverable begins with a four- or five-line factual timeline, not a confident story about the largest price on a chart.
02Select evidence that can answer the question
Match each question to an observation. Use the applicable price series for the financial question, metered or explicitly defined interval-average quantities for the energy calculation, and unit targets, availability, bids, constraints and flows for operational mechanisms. A dispatch target alone does not prove delivered metered energy; an installed capacity number does not prove available supply in the interval.
AEMO's MMS documentation provides a route to current table definitions and market-data reports. Before extracting real records, write down the table, primary keys, field definitions, interval convention and revision treatment. Some participant information has different access conditions. Do not invent missing bids or treat a public dashboard as if it contains every settlement or operational field.
Join tables only after deciding how region, interval, intervention/run identifiers and revisions distinguish records in the selected data model. Reconcile row counts before and after every join. Preserve absent observations as missing until their meaning is investigated; converting a missing price to zero invents a free-energy interval. Topics 31 and 32 provide a synthetic cleaning lab before this real-data extraction task.
03Reconcile the financial effect before explaining its cause
Use the case's separate original synthetic dataset, not June 2022 observations: four five-minute intervals with average customer loads 120, 180, 240 and 180 MW, and prices A$50, 100, 300 and 150/MWh. Each energy quantity is average MW × 5/60 hours: 10, 15, 20 and 15 MWh. Energy-only costs are A$500, 1,500, 6,000 and 2,250, totalling A$10,250 for 60 MWh.
The customer-weighted unit cost is 10,250/60 = approximately A$170.83/MWh. The simple mean price is A$150/MWh; multiplying it by 60 MWh gives A$9,000 and understates cost by A$1,250. Higher consumption coincides with higher prices in this example. That explains the arithmetic difference, not why the market price changed.
Declare the financial boundary. This example excludes contracts, losses, network and retail charges, ancillary services, taxes, prudentials and compensation. It is neither a complete retail bill nor a participant settlement. Before adding any of those components, identify their quantities, reference prices, applicable rules and cash-flow direction. Never multiply a regional price by a unit dispatch target and present it as an audited invoice.
04Decompose change without pretending it proves causation
Compare the observed teaching profile with a stated reference: 120 MW and A$50/MWh in every interval. Reference energy is 40 MWh and cost A$2,000. The observed cost increase is A$8,250. This reference is a chosen analytical baseline, not a forecast or a claim about what would really have happened without the event.
For each interval write Q = Q0 + ΔQ and P = P0 + ΔP. Then QP − Q0P0 = Q0ΔP + P0ΔQ + ΔQΔP. Summing the rows gives A$4,000 of price change at reference volume, A$1,000 of volume change at reference price and A$3,250 of interaction. The three terms add exactly to A$8,250. Omitting interaction would leave a large unexplained difference.
This is an accounting decomposition, not a causal market model. Changing price first and then quantity allocates the interaction differently from changing quantity first; disclose the method. To argue that an outage caused a price movement, investigate availability, ramp limits, bids, demand, imports, constraints and interventions, and test a plausible alternative explanation. A constrained rerun requires a validated model and inputs; the cost identity does not replace it.
05Read the June 2022 record in its own context
AEMO’s review covers 10–24 June 2022. Administered pricing began in Queensland on 12 June and NSW, Victoria and South Australia on 13 June. The spot market suspension began on the afternoon of 15 June amid interacting operational and commercial pressures. Its contemporary summary and later incident report should be read together. The dated media release records the formal lifting at 14:00 AEST on 24 June. These are historical facts, not a claim that today's price settings, procedures or compensation arrangements are unchanged.
Use the report to extract three categories: documented system conditions, operator actions, and subsequent findings. Locate the sequence involving fuel pressures, generator availability, administered pricing, directions and suspension. Record the page or notice supporting each link. Distinguish the return of normal pricing during the staged process from the formal end of suspension; do not compress different milestones into one timestamp.
Your historical task is to identify what each source establishes and what it leaves unresolved. Prepare two competing mechanism explanations and the evidence needed to discriminate between them. Do not infer participant intent from an availability change alone. The four-row CSV is a separate teaching exercise and contains no reconstructed prices, volumes, losses or compensation from June 2022.
06Turn the reconstruction into a controlled response
Write an event note with six parts: decision required; verified sequence; quantified exposure; competing explanations; action; and review trigger. Label each material statement as observation, assumption, model output or judgement. An appropriate first response can be to obtain a missing constraint or settlement record, not to increase a trading position on the basis of a visual correlation.
Independent transfer task: in the synthetic profile, move 5 MWh from the third interval to the first, keeping total energy fixed and assuming prices do not change. Recalculate the load profile and cost, then explain what operational flexibility would be needed. The arithmetic is not proof that a real customer can shift the load or that prices remain fixed after a large demand response. Identify rebound, service requirements and connection limits before recommending action.
For a real-data follow-up, select one bounded historical interval window, retrieve the applicable public records and preserve the original files. A reviewer should check your timestamp convention, joins, revisions, mechanism evidence and alternative explanation. Submit a reproducible workbook, a short timeline and a one-page memo. Neither a correct cost bridge nor a quiz pass alone establishes independent event-analysis competence.
Watch the explanation
Key terms in plain English
- Dispatch
- The operational process of determining output and consumption targets, subject to offers, demand and system constraints. A target is not a meter reading.
Supporting diagrams
Three clocks in one event
A schematic example, not an actual incident timeline.
- 01 · Physical event10:02
When a condition changes
- 02 · Interval label10:05
Check the dataset's start/end convention
- 03 · Published evidence10:07
When the notice becomes available
Explain the entire cost bridge
Four synthetic five-minute intervals; energy-only customer costs.
- 01 · ReferenceA$2,000
120 MW and A$50/MWh throughout
- 02 · Changes+A$8,250
Price 4,000 + volume 1,000 + interaction 3,250
- 03 · Observed scenarioA$10,250
60 MWh at a weighted A$170.83/MWh