Accuracy
Reconcile MW × hours, the buyer's swap sign and both load cases; do not net a financial position against a physical limit.
Lessons
Brief a decision-maker with evidence, uncertainty and action.
A fictional retailer serves a constant 40 MW load in each of two consecutive two-hour blocks. Spot prices are A$70/MWh and A$250/MWh. A fixed-for-floating swap covers 30 MW in both blocks at A$100/MWh. Compare the original load with reducing only the second block to 35 MW. The financial contract is unchanged and does not reserve physical supply capacity.
For each dimension, record 0 — Not yet, 1 — With guidance, or 2 — Independent. Explain your rating. Correct material physical or numerical errors before sharing; do not average them away.
Reconcile MW × hours, the buyer's swap sign and both load cases; do not net a financial position against a physical limit.
Retain input rows, formulas and source versions so another reader can reproduce the result.
Test the price sensitivity and identify the maximum unpriced service cost that could eliminate the modelled saving.
Recommend proceed, modify or defer with a named decision role, missing evidence and a review trigger.
Use the Self-review tab to rate your evidence against all four dimensions. A quiz does not complete this capstone. No automatic marking, tutor review or credential is provided; arrange qualified feedback separately.
Original: 160 MWh and A$ 18,400 net cost. Reduce the second block to 35 MW: 150 MWh and A$ 15,900. Energy-cost reduction: A$ 2,500 before lost-service cost.
At a second-block price of A$150/MWh, original net cost is A$ 16,400; reduced-load cost is A$ 14,900. The swap is unchanged between load cases. A numerical match alone does not validate the recommendation.
Background study is separate from the decision pack. Do not combine unrelated teaching datasets as if they describe one real site.
Keep the decision memo within 800 words, or the shorter limit in your brief. State the recommendation, three decision-driving numbers with sources or assumptions, one rejected alternative, and the largest risk with its owner and review trigger. Separate facts, modelled results and missing evidence. Keep your calculation workbook separately and record its filename, version and key results here. Do not enter confidential information.
Draft notes are saved in this browser when storage is available; they are not submitted or synced.