Accuracy
Reconcile the 35 MW stress boundary, IT/facility ratio and both backup constraints; do not claim safe operation from arithmetic alone.
Lessons
Integrate engineering, markets, law, finance, data, safety and people.
Use the worked data-centre project as an evidence pack. A proposed staged load reaches the normal 42 MW import ceiling, but a new planning scenario reduces available import to 35 MW for the hot two-hour interval. Critical load remains 16 MW. Backup remains 8 MWh usable AC energy with a 12 MW power limit. Prepare a decision pack that connects physical feasibility, commercial exposure, control-system evidence and accountable escalation.
For each dimension, record 0 — Not yet, 1 — With guidance, or 2 — Independent. Explain your rating. Correct material physical or numerical errors before sharing; do not average them away.
Reconcile the 35 MW stress boundary, IT/facility ratio and both backup constraints; do not claim safe operation from arithmetic alone.
Retain the source case version, changed inputs and linked workbooks; distinguish this scenario from historical or operational data.
Separate screening, engineering validation and operating authority; resolve contradictions and specify missing evidence.
Present a conditional decision with owners, go/no-go gates and review triggers, ready for qualified review.
Use the Self-review tab to rate your evidence against all four dimensions. A quiz does not complete this capstone. No automatic marking, tutor review or credential is provided; arrange qualified feedback separately.
30 MW IT × 1.40 = 42 MW facility demand. Against 35 MW import, that is a 7 MW gap. At the same ratio, 35 ÷ 1.40 = 25 MW IT is the arithmetic import ceiling, not an operating approval.
8 MWh ÷ 16 MW is 30 minutes on energy alone, but 12 MW backup cannot serve 16 MW of critical load. The 4 MW power shortfall remains. A demand or contract change does not resolve it.
Background study is separate from the decision pack. Do not combine unrelated teaching datasets as if they describe one real site.
Clean a small dataset, test a forecast and explain a cost exposure. Use Excel or your preferred analysis tool; this page checks selected results, not your code or judgement.
Your inputs and memo stay here when you switch sections, topics or resources in this open page. Export before reloading, closing or opening another page. This is a temporary draft, not an account-saved submission.
An interval is a fixed period of time. This lab uses five-minute intervals. A revision is an updated version of a record; keep the latest valid version at the stated cutoff rather than adding both versions.
MAE means mean absolute error: average the size of each forecast error, ignoring its sign. A zero average signed error can hide errors that cancel out. First reproduce one row; then follow the full method below.
Synthetic site demand in NSW1: six five-minute intervals ending 09:05–09:30 AEST on 18 September 2026. Average MW, not instantaneous SCADA or dispatch targets. Extract cutoff: 10:00 AEST. All listed revisions are available by the cutoff. Spot energy cost only: exclude losses, network and retail charges, taxes, hedges and credit. Forecasts are assumed issued at 08:55 using only earlier information; they are invented, not fitted models.
| interval_end_aest | site | region | revision | average_mw |
|---|---|---|---|---|
| 2026-09-18 09:05 | SITE1 | NSW1 | 1 | 60 |
| 2026-09-18 09:10 | SITE1 | NSW1 | 1 | 100 |
| 2026-09-18 09:10 | SITE1 | NSW1 | 2 | 120 |
| 2026-09-18 09:15 | SITE1 | NSW1 | 1 | 180 |
| 2026-09-18 09:20 | SITE1 | NSW1 | 1 | 120 |
| 2026-09-18 09:20 | SITE1 | NSW1 | 1 | 120 |
| 2026-09-18 09:25 | SITE1 | NSW1 | 1 | 60 |
| 2026-09-18 09:30 | SITE1 | NSW1 | 1 | 180 |
| interval_end_aest | region | aud_per_mwh |
|---|---|---|
| 2026-09-18 09:05 | NSW1 | 50 |
| 2026-09-18 09:10 | NSW1 | -20 |
| 2026-09-18 09:15 | NSW1 | 100 |
| 2026-09-18 09:15 | VIC1 | 40 |
| 2026-09-18 09:20 | NSW1 | 200 |
| 2026-09-18 09:25 | NSW1 | 0 |
| 2026-09-18 09:30 | NSW1 | 80 |
| interval_end_aest | baseline_mw | candidate_mw |
|---|---|---|
| 2026-09-18 09:05 | 60 | 65 |
| 2026-09-18 09:10 | 100 | 115 |
| 2026-09-18 09:15 | 160 | 170 |
| 2026-09-18 09:20 | 100 | 130 |
| 2026-09-18 09:25 | 80 | 65 |
| 2026-09-18 09:30 | 160 | 175 |
No Excel or SQL experience? Start with Topic 1's unit conversions and a spreadsheet basics course. This lab teaches an energy workflow, not every feature of an analysis package.
Clean demand is 60, 120, 180, 120, 60, 180 MW. Interval energy is 5, 10, 15, 10, 5, 15 MWh: 60 MWh total. Interval costs are A$250, −A$200, A$1,500, A$2,000, A$0 and A$1,200: A$4,750 total. The volume-weighted price is A$79.17/MWh; the simple interval-price average is A$68.33/MWh. The two calculations use different weights.
Baseline MAE is 16.67 MW; candidate MAE is 6.67 MW. Candidate signed mean error is zero but individual errors remain. A price-only stress adds A$1,000 (total A$5,750); the joint stress adds A$1,600 (total A$6,350). Six synthetic points do not establish model superiority in production or a probabilistic loss measure.
Download the independent full-day CSV
A separate synthetic site-day starting 19 September 2026: 288 five-minute intervals ending from 00:05 AEST to 00:00 the following day. The raw file includes one exact duplicate and one missing candidate prediction. All power values are interval averages. Forecasts are invented teaching outputs assumed issued before the day, not evidence of a fitted model. Prices, load and errors are deliberately simplified.
Attach your clean table, formulas or script and labelled chart to a one-page memo. State the decision, evidence, exclusions, alternative and next action. Export before reloading or leaving this page; nothing is submitted to a reviewer.
Numerical checks do not approve the chart, data treatment or recommendation. Obtain a competent review before representing this as workplace capability.
Keep the decision memo within 800 words, or the shorter limit in your brief. State the recommendation, three decision-driving numbers with sources or assumptions, one rejected alternative, and the largest risk with its owner and review trigger. Separate facts, modelled results and missing evidence. Keep your calculation workbook separately and record its filename, version and key results here. Do not enter confidential information.
Draft notes are saved in this browser when storage is available; they are not submitted or synced.